Description
Hardware & Electrical Specifications
‑ Manufacturer: GE General Electric ‑ Compatible System: Speedtronic Mark‑V Turbine Control ‑ Functional Acronym: TCEB (Protective Termination Expander Board) ‑ Signal Types Handled: • Overspeed pulse signals from magnetic speed pickups • UV flame‑detector input signals and flame‑detector 335VDC power supply output • PT voltage transformer and CT current transformer scaled measurement signals • Alarm drive output for local audible horn ‑ Inter‑Board Connectors: Multiple multi‑pin ribbon‑cable headers for connection to PTBA terminal board, TCEA overspeed boards and TCCB core controller ‑ On‑Board Jumpers: Configurable Berg‑style jumpers for signal routing and hardware mode selection. All jumper positions must be exactly duplicated during replacement ‑ On‑Board Device: Integrated audible alarm horn for local fault alert ‑ Power Source: Powered via system inter‑board connectors ‑ PCB Finish: Conformal coated multilayer FR‑4 PCB ‑ Compatibility Restriction: Works only for Mark‑V systems; not compatible with Mark‑VI / Mark‑VIe control racks.
Environmental Specifications
‑ Operating Temperature: 0 °C ~ +60 °C ‑ Storage Temperature: −40 °C ~ +85 °C ‑ Relative Humidity: 5%‑95 % non‑condensing ‑ Installation Environment: Control cabinet interior, Pollution Degree 2 ‑ EMC: Designed for power‑plant cabinet EMI and switching‑transient conditions
Mechanical Data
‑ Physical Dimension: approx 265 mm × 160 mm ‑ Mounting: Standard core rack slot mounting ‑ Weight: approx 0.75 kg
Core Functions
- Safety‑signal conditioning & distribution: Receives overspeed, flame‑detector signals from PTBA termination board, routes conditioned signals to triple‑redundant TCEA overspeed protection boards for trip‑logic voting.
- PT/CT signal scaling: Conditions voltage and current transformer signals for generator voltage and current measurement, sends scaled data to TCCB core control board.
- Flame‑detector power supply: Provides regulated 335 VDC operating power for UV flame‑detector field devices.
- Local audible alarm: Drives onboard horn to give on‑site audible alert for critical turbine protective events.
- Signal interconnection: Multi‑pin ribbon‑cable headers realize signal transmission between field termination hardware and internal safety & control processor boards.
Installation, Replacement & Critical Warnings
- Complete system power‑down and lock‑out procedure required before servicing. Non‑hot‑swappable. ESD wrist‑strap protection is mandatory when handling the PCB assembly.
- Record all original jumper positions prior to removal. Incorrect jumper settings will misroute overspeed or flame‑detector signals and compromise turbine safety protection.
- Firmly secure all multi‑pin ribbon‑cable connectors; loose connections cause intermittent loss of critical protective signals.
- After power restoration, perform full signal check: verify speed‑pulse transmission, flame‑detector power output, PT/CT measurement values and alarm‑horn operation.
-
Common failure mode: Transient surges from field wiring may damage signal‑conditioning circuits, resulting in missing safety signals to downstream TCEA protection boards.