Description
Hardware & Electrical Specifications
- Model:IS200TPROS1CBB
- Part Number:IS200TPROS1CBB
- Module Type:TPRO‑S1 Conformal‑Coated Emergency Protection Terminal Board
- Mounting:Cabinet panel mounting inside turbine control cabinet
- Power supply:24/28 VDC auxiliary power supplied by VPRO protection processors
- Input channels: ‑ Multi‑channel MPU magnetic‑pickup high‑frequency pulse inputs for overspeed monitoring ‑ Multi‑channel thermocouple input (J, K, T, E type) for exhaust and bearing temperature ‑ Analog input channels for process protection transmitters ‑ Discrete contact inputs for ESD emergency shutdown and backup protection contacts
- Isolation:Built‑in isolation transformers, high galvanic isolation to reject plant ground‑loop interference
- Interface:Removable barrier‑type screw terminal blocks for field wiring; multiple multi‑pin ribbon connectors for VPRO processor interconnection
- PCB treatment:S‑type conformal coated (CBB revision) for dust‑moisture‑corrosion resistance
- On‑board protection:ESD protection, MOV surge suppression, transient absorption circuit for safety‑signal loops
- Compatibility note:Cannot run standalone; must match Mark VI VPRO protection processor; TMR triple‑redundant system requires three‑board consistency verification; overspeed‑protection simulation test mandatory after replacement.
Environmental Specifications
- Operating temperature:‑40 ℃ ~ +70 ℃
- Storage temperature:‑40 ℃ ~ +85 ℃
- Relative humidity:5%‑95% non‑condensing
- Installation location:Indoor turbine control cabinet
- EMC compliance:IEC 61000‑6‑2
- Certifications:CE
Mechanical Data
- Weight:approx 1.45 kg
- Dimension:330 mm × 178 mm × 55 mm
- Handling note:ESD‑sensitive PCB; safety‑critical speed‑measuring circuit, anti‑static wrist‑strap mandatory during handling
- Recommended wire cross‑section:0.75‑2.5 mm² shielded twisted‑pair copper / dedicated thermocouple extension cable for field sensor wiring
- Terminal tightening torque:0.6‑1.0 N·m
Main Functions
- Removable screw‑terminal field termination for turbine safety‑related signals: MPU speed‑pickup pulse signals, exhaust thermocouple temperature signals, generator analog protection signals, emergency shutdown ESD contact signals.
- Built‑in isolation transformers provide galvanic isolation between plant field wiring and VPRO protection logic, eliminate ground‑loop and high‑EMI turbine‑hall interference.
- Condition high‑frequency speed pulse, millivolt‑level thermocouple and discrete trip signals, transmit to three VPRO protection processors for emergency overspeed EOS calculation, over‑temperature protection and TMR voting‑logic processing.
- On‑board signal conditioning for weak thermocouple and high‑frequency MPU pulse signals.
- On‑board channel self‑diagnosis: detect MPU sensor open‑/short‑circuit, thermocouple fault, field‑loop abnormal status, report fault alarm to turbine main controller.
- On‑board self‑diagnosis: detect auxiliary power loss and ribbon‑cable link failure.
- LED status indication: ‑ Green LED:Terminal‑board auxiliary power normal ‑ Yellow LED:Signal input & ribbon‑cable link communication active ‑ Red LED:Field‑channel fault / overspeed condition / link communication loss alarm
Installation & Wiring Requirements
- Cut off rack power supply before replacement. Hot‑swap is forbidden. Strict anti‑static protection when handling PCB board.
- Secure panel mounting firmly; ensure all multi‑pin ribbon‑cable connectors fully locked without loose contact.
- Field sensor wiring strictly follow GE Speedtronic Mark VI wiring manual: MPU speed cables and thermocouple cables must use dedicated shielded extension cables, strictly separated from high‑power cables; connect shielding to dedicated ground terminal.
- Complete protective grounding according to GE Speedtronic system specification.
- After replacement: verify ribbon‑cable link status, check raw MPU pulse signal and thermocouple temperature reading, simulate overspeed and protection‑trip input, validate VPRO protection‑logic response before commissioning.
- Replacement note: For TMR triple‑redundant safety‑loop application, three‑set IS200TPROS1CBB channel consistency must be verified; full emergency‑protection‑loop simulation test mandatory after swap.



-1-300x300.jpg)